Road transport, highways projects hit slow lane

Muneerabad-Mahaboobnagar rail project is the most-delayed project as it’s overdue by 276 mths: Govt report

Update:2022-11-27 21:41 IST

New Delhi: The road transport and highways sector has the maximum number of delayed projects at 243, followed by railways at 114 and the petroleum sector at 89, showed a government report.

In the road transport and highways sector, 243 out of 826 projects are delayed. In railways, out of 173 projects, 114 are delayed, while in petroleum sector, 89 out of 142 projects are delayed, as per the latest flash report on infrastructure projects for October 2022.

The Infrastructure and Project Monitoring Division (IPMD) is mandated to monitor central sector infrastructure projects costing Rs150 crore and above based on the information provided on the Online Computerised Monitoring System (OCMS) by the project implementing agencies. The IPMD comes under the Ministry of Statistics and Programme Implementation.

The report showed that the Muneerabad-Mahaboobnagar rail project is the most-delayed project. It is delayed by 276 months. 