Highways projects mostly delayed

248 projects in road transport & highways sector followed by 116 in railways and 88 in petroleum sectors are far behind the schedule: Govt report

image for illustrative purpose

Highways projects mostly delayed
X

10 Oct 2022 1:43 AM IST

New Delhi: The road transport and highways sector has the maximum number of delayed projects at 248, followed by railways at 116 and petroleum sector at 88, showed a government report.

In the road transport and highways sector, 248 projects are delayed with respect to their original schedule out of the 831 monitored, as per the latest flash report on infrastructure projects for August 2022. Similarly in railways, out of 173 monitored projects, 116 are delayed, while for petroleum, 88 out of 139 projects are delayed.

The Infrastructure and Project Monitoring Division (IPMD) is mandated to monitor central sector infrastructure projects costing Rs150 crore and above, based on the information provided on the Online Computerised Monitoring System (OCMS) by the project implementing agencies. The IPMD comes under the Ministry of Statistics and Programme Implementation.

The report showed that the Muneerabad-Mahaboobnagar rail project is the most delayed project. It is delayed by 276 months. The second most delayed project is the Belapur-Seawood-Urban Electrified Double Line, which is delayed by 228 months.

Highways projects IPMD OCMS 